Skip to content
Complimentary intro call, 24-hour response
Pusula Marine PM
New Build & Shipyard Financing

Shipbuilding Contract: Standard Templates, Critical Clauses, Negotiation

For a newbuild yacht or ship, the main contract is the shipbuilding contract. While Saleform / MOA is used for second-hand purchases, newbuild uses SAJ, NSF Newbuilcon or BIMCO Newbuildcon templates. This guide walks through the structure and negotiation points.

What this guide covers

  • The structure of a newbuild contract
  • Standard templates (SAJ, NSF Newbuilcon, BIMCO Newbuildcon)
  • Critical clauses — spec, milestone payments, penalty clauses
  • Refund guarantee, performance guarantee
  • Negotiation pressure points

Note: This page is educational. It is not a substitute for legal advice — for a project-specific contract, your legal counsel and financing advisor must work side by side.

Standard templates

Three main templates on the newbuild side:

1. SAJ Form (Shipbuilders' Association of Japan)

  • The most widely used template
  • Originated from Japanese yards, but adopted globally
  • Slightly more balanced toward the yard
  • Detailed milestone payment structure

2. NSF Newbuilcon (Norwegian Shipbuilding Contract)

  • Norway-based
  • Slightly more balanced toward the owner
  • Common across European yards

3. BIMCO Newbuildcon

  • Published by BIMCO in 2007
  • A modern alternative
  • Designed to be balanced for both owner and yard
  • Some clauses defined more clearly

On the yacht side: SAJ or a project-specific custom contract is most common. Superyacht projects often use custom drafting (every project differs).

Core structure

A shipbuilding contract typically contains the following sections:

1. Definitions + parties

  • Owner + Builder (Yard) identities
  • Vessel description (hull number)
  • Reference documents (spec, GA drawings)

2. Description of the vessel

  • Specification document reference
  • Class society + flag determined
  • Main dimensions + parameters
  • Standard vs. optional systems

3. Price + payment structure

  • Contract price
  • Currency (typically € or $)
  • Milestone payments + triggers
  • Late payment penalties

4. Delivery + sea trial

  • Target delivery date
  • Sea trial procedure + acceptance criteria
  • Late delivery penalty (liquidated damages)
  • Owner's right to cancel (if late delivery cap exceeded)

5. Performance guarantees

  • Speed guarantee (e.g. service speed in kn)
  • Fuel consumption guarantee
  • Deadweight / cargo capacity (commercial ship)
  • If guarantee fails: liquidated damages

6. Variation orders (spec change)

  • Variation order procedure
  • How the price impact is calculated
  • Delivery date impact
  • Approval process

7. Inspection + class society

  • Owner's right of inspection (owner's representative)
  • Class society surveys
  • Steps requiring prior approval
  • Yard's obligation on rejected work

8. Refund guarantee + performance guarantee

  • Refund guarantee terms
  • Identity of the issuing bank
  • Guarantee amount + scope
  • Performance guarantee (if any)

9. Force majeure + suspension

  • Force majeure definition
  • Notification procedure
  • Right to time extension
  • Termination right on long suspension

10. Risk transfer + insurance

  • Period during which risk sits with the yard (until delivery, typically)
  • Builder's risk insurance requirement
  • Owner's right to coordinate insurance

11. Warranty period

  • Typically 12–24 months post-delivery
  • Warranty scope (structural defects, system defects)
  • Excluded scenarios
  • Warranty claim procedure

12. Arbitration + governing law

  • Dispute resolution seat (typically London LMAA)
  • Governing law

Critical clauses — what to watch

Refund guarantee chain

Each milestone payment exposes the owner to yard risk. Refund guarantee terms:

  • Issuing bank: local to the yard, or international?
  • Amount: paid milestone + interest, or principal only?
  • Call conditions: under what circumstances can the owner call?
  • Tenor: does it renew with each milestone?

A weak clause → if the yard fails, the owner loses money.

Late delivery penalty (liquidated damages)

  • Daily / weekly penalty amount
  • Cap (e.g. 5% of contract price)
  • Owner's cancellation right beyond the cap
  • Force majeure time extension

Performance guarantees

  • Speed measurement procedure (test conditions must be explicit)
  • Fuel consumption measurement procedure
  • Margin (e.g. 3% deviation tolerance) defined
  • If guarantee fails: refund or compensation?

Variation order structure

  • Can the owner change spec at any point?
  • Price impact: transparent yard calculation?
  • Delivery date impact automatic, or negotiated?
  • Can the yard reject a variation?

Negotiation — who wants what?

Owner typically wants:

  • Lower milestone payments (cash flow comfort)
  • Higher refund guarantee amount
  • Strong performance guarantees
  • Clear spec compliance standards
  • Broad inspection rights

Yard typically wants:

  • Higher milestone payments (cash flow)
  • Lower performance penalties
  • Flexibility on variation orders
  • Broad force majeure definition
  • Short warranty period

Negotiation finds the middle. An experienced broker / legal counsel manages the process.

Coordination with the financing process

Points where the shipbuilding contract meets the financing side:

  1. Drawdown conditions — the bank's milestone-disbursement conditions are tied to the contract triggers
  2. Refund guarantee assignment — refund guarantee is typically assigned to the bank (collateral)
  3. Owner's representative report — the bank wants this before every drawdown
  4. Class society survey — the bank also tracks this
  5. Delivery clauses — the bank's drawdown timing must align with the contract delivery clauses

FAQ

Who drafts the shipbuilding contract?

Typically the owner's legal counsel prepares the draft (off a standard template), the yard side revises, and negotiation proceeds. Experienced yacht lawyers exist on the yacht side; maritime law specialists on the commercial ship side.

SAJ or NSF — which one?

Depends on the yard's geography. Asian yards know SAJ; European yards know NSF. BIMCO Newbuildcon is a modern alternative for both. A standard template is the starting point — project details get layered on top.

Can a newbuild contract be signed without a refund guarantee?

Practically no — too risky for the owner. Possible on small projects, but mandatory in projects with professional financing.

Can variation orders increase the price significantly?

Yes — a common surprise. This is why finalising the spec before contract signature + transparent variation order procedures are critical. Owner asks for a change, yard quotes, owner accepts, then it's signed.

What does the warranty period cover?

Typically: structural defects, main engine defects, system defects (under normal use). Excluded: wear and tear, normal damage, owner misuse, third-party damage.

Related


Talk to us about your project: let us plan the shipbuilding contract negotiation + financing coordination together. Reach out via the contact form.

Request a Call

Let's design the right financing structure for your project.

A complimentary conversation. We reply within 24 hours.

Direct Contact

Reply within 24 hours. The conversation is complimentary.